Installation and operation steps of eye drops filling machine
Release time:
2024-05-04 09:29
Eye drops filling machine is an automated machine, so easy to pull bottles, bottle pads, bottle caps size requirements are uniform. You must first use the rocker to rotate the machine to see if there is any abnormality in its rotation, and it is indeed determined that it is normal before driving. When adjusting the machine, the tools should be used properly. It is strictly forbidden to use too large tools or use too much force to remove the parts so as not to damage the parts or affect the performance of the machine. Every time the machine is adjusted, the loose screw must be tightened, and the machine can be driven only after turning the machine with a rocker handle to see if its action meets the requirements. The machine must be kept clean. It is strictly forbidden to have oil stains, liquid medicine or glass chips on the machine to avoid corrosion of the machine. Therefore, it is necessary to remove liquid medicine or glass chips in time during the production process of the machine. Before the shift, all parts of the machine surface should be cleaned once, and clean lubricating oil should be added to each activity department. It should be scrubbed once a week, especially the place that is not easy to clean in normal use or blown with compressed air. After the machine is unpacked, first check whether the random technical data is complete and whether the machine is damaged during transportation, so as to solve it in time. Install and adjust the feed assembly and discharge assembly according to the outline drawing in this manual. Add new lubricating oil to each lubricating point. Turn the machine with the rocker handle to check whether the machine is running in the correct direction (facing the motor spindle is counterclockwise), and the machine must be protected and grounded.
eye drops filling machine operation steps:
1. Place the filled liquid bottle upside down on the work basket, and check that the lower opening of the liquid bottle should be aligned.
2. Place the vacuum basket in the vacuum tank, cover the quick-open tank lid and lock it.
3. Close the vent valve and liquid inlet valve, open the vacuum pump, adjust the real air conditioner connecting valve to make the vacuum degree (depending on the trial filling volume) meet the process requirements, and step on the foot pedal to insert liquid into the bottom of the filled liquid bottle.
4. Slowly open the liquid inlet valve, then the liquid level in the filling rises, and at the same time open the vent valve to keep the liquid level between the liquid level specified by the sight glass.
5. When the pointer of the vacuum gauge is in the 0 state, it is proved that the liquid filling is completed, return the foot collapse plate, and open the quick-opening tank cover to take out the liquid bottle that is also filled.
6. For troubleshooting of vacuum mercury, see (operating instructions for XD series but grade rotary vane vacuum pumps). If the vacuum pump is not used for a long time (for more than seven days), the used oil in mercury should be drained, washed and replaced with new oil to prevent water in the oil from corroding the pump body.